Project for Foreign Economic & Technical Cooperation

No:96001
  1. Project Information:
    1. Project Summary: To produce 4 million sets of computer monitor (14'',15'',17'') annually
    2. Total Investment (US$) :150 million
    3. Expected Foreign Capital involved: 60%
    4. Expected Terms of Foreign Investmet: Cash, equipment, technology
    5. Domestic markets Demand: 2 million sets in 1996, 8 million sets in 2000
    6. Targeted Annual Turnover(US$): 760.00 million
    7. Targeted Annual Taxes and Profits (US$): 80.00 million
    8. Rate of Return:
    9. Payoff Period: 3.0 years
    10. Export Proportion: 70%
    11. Terms of Chinese Investment: 130,000 m land-use right, 32000m workhouse, 160 sets equipment, and production technology.
    12. Cooperation Mode: Joint venture
  2. Present Situation of the Project:
    1. Project Applied or Approved:
    2. Specific Plan Completed or not: started in January, 1997, will be completed in june, 1998
  3. Enterprise Current Situation:
    1. Name: Nanjing Tontru Information Industry Group Co.
    2. 2. Responsible Authorities: Nanjing Municipal Government
    3. 3. Business Scope and Production: PC(100,00 sets ),system integrate, software
  4. Liaison Person:
    1. 1. Name: Yuan Ping
    2. 2. Tel:4541655
    3. 3. Fax:4541666
    4. 4. Addr: Room 708,Changjiang Trade Building, 99, Changjiang Road, Nanjing
  5. Additional Information:


No:96002
  1. Project Information:
    1. Project Summary:To produce 300 million picecs INSB "Hall Effect" components and reducers annually
    2. Total Investment (US$): 20 million
    3. Expected Foreign Capital Involved: 50%
    4. Expected Tterms of Foreign Investment: Cash, technique
    5. Domestic markets Demand: 700-1000 million pieces annually
    6. Targeted Annual Turnover(US$): 60.00 million
    7. Targeted Annual Taxes and Profits(US$):11.50 million
    8. Rate of Return: 30%
    9. 9.Payoff Period: 3.5 years
    10. Export Proportion: 70%
    11. Terms of Chinese Investment: 50 million yuan (RMB) cash, 5400 m workhouse, 150 sets equipment, existing production technique
    12. Cooperation Mode: Joint venture, processing/assembling of supplied materials
  2. Present Situation of the Project:
    1. Project Applied or Approved: Applied
    2. Specific Plan Completed or not: No
  3. Enterprise Current Situation:
    1. Name: Nanjing Semi- conductor Device General Factory
    2. Resiness Scope and Production: Nanjing ELectronic Industry Bureau
    3. Business Scope and Production: "Hall Effect" components, Hall circuit reducers and transistors with an annual production of 40 million pieces
  4. Liaison Person:
    1. Name: Xiao Yuxiong
    2. Tel: 6626562
    3. Fax: 2202041
    4. Addr:No.99 Gongyuan Street, Nanjing
  5. Additional Information: An input of 35 million yuan(including US$ 2.5 million) has been used for technical improvement and product development during the "Eigth Five-Year Plan" period

No: 96003
  1. Project Information:
    1. Project Summary: To produce 10 million chassis, 10 million power supply units and 3 million speaker systems annually
    2. Total Investment (US$): 19 million
    3. Expected Foreign Capital Involved: 80%
    4. Expected Terms of Foreign Investment:
    5. Domestic Markets Demand: Chassis and power supply 3 million sets,etc.
    6. Targeted Annual Turnover(US$): 60.00 million
    7. Targeted Annual Taxes and Profits (US$): 5.00 million
    8. Rate of Return: 25%
    9. Payoff Period: 4.0 years
    10. Export Proportion: 80%
    11. Terms of Chinese Investment: 270,000 m land-use right, 29900m #178 factory, 180 sets of equipment, and mold technology.
    12. Cooperation Mode: Joint venture
  2. Present Situation of the Project:
    1. Project Applied or Approved: The project plan will be finished by DEC., 1996.
    2. Specific Plan Completed or not: Started in January, 1997, completed in December, 1998.
  3. Enterprise Current Situation:
    1. Name: Nanjing Tontru Information Industry Group Co.
    2. Responsible Authorities: Nanjing municipal Government
    3. Business Scope and Production: PC(100,000 sets),systems integrated, software, etc
  4. Liaison person:
    1. Name: Yuan Ping
    2. Tel: 4541655
    3. Fax: 4541666
    4. Addr: Room 708, Changjiang Trade Building, 99 Changjiang Road, Nanjing
  5. Additional Information:

No:96004
  1. Project Information:
    1. Project Summary: To produce 3 million sets of feedback tranformers and deflection coils for monitors annually
    2. Total Investment (US$): 10 million
    3. Expected Foreign Capital Involved: 50%
    4. Expected Terms of Foreign Investment: cash
    5. Domestic market Demand: 15 million pieces/year
    6. Targeted Annual Turnover (US$): 38.55 million
    7. Targeted Annual Taxes and Profits (US$): 5.78 million
    8. Rate of Return: 30%
    9. Payoff Period: 3.0 years
    10. Export Proportion: 70%
    11. Terms of Chinese Investment: 30 million yuan RMB in cash, 20000 m land use right, 4000 m factory, 200 sets of equipment.
    12. Cooperation Mode: Joint venture, cooperative joint venture
  2. Present Situation of the Project:
    1. Project Applied or Approved:
    2. Specific Plan Completed or not: Expected to be finished by 1998
    3. Business Scope and Production:
  3. Enterprise Current Situation:
    1. Name: Nanjing Radio & Television Assemblies Factory
    2. Responsible Authorities: Nanjing Electronic Industry Bureau
  4. Liaison Person:
    1. Name: Zhang Minsheng
    2. Tel: 3421105
    3. Fax: 3425739
    4. Addr: No.100 North Huju Road, Nanjing
  5. Additional Information:

No:96005
  1. Project Information:
    1. Project Summary: Optical Fiber Loop carrier system
    2. Total Investment (US$): 10 million
    3. Expected Foreign Capital Involved: 50%
    4. Expected Terms of Foreign Investment: Cash,equipment, technology
    5. Domestic markets Demand: more than 0.6 billion user's lines
    6. Targeted Annual Turnover (US$): 13.90 million
    7. Targeted Annual Taxes and Profits (US$): 3.45 million
    8. Rate of Return : 27%
    9. Payoff Period: 3.0 years
    10. Export Proportion:
    11. Terms of Chinese Investment: 38,000 m of land -use right, 12000 m of factory, 166 sets of equipnent
    12. Cooperation Mode: Joint venture, cooperative joint venture
  2. Present Situation of the Project:
    1. Project Applied or Approved: applied
    2. Specific Plan Completed or not: No
  3. Enterprise Current Situation:
    1. Name: Jiangsu Gaonen Group Corp
    2. Responsible Authorities: Nanjing new & High-tech Industrial Development Zone
    3. Business Scope and Production: Electronic communicarion
  4. Liaison Person:
    1. Name: Yuan Yinming
    2. Tel: 8841089
    3. Fax: 8843843
    4. Addr:Division of Indstrial Development, P.O. Box 3209, Nanjing
  5. Additional Information:

Return to www.ChinaPages.Com
ChinaPages© Copyright 1996
DiFe - Hope Internet Information Developing Co., Ltd.Hangzhou, China
Contact: Webmaster